Engineering note Verification China Machinery Group — Shanghai
Level survey and testing on a treated formation
The level survey is the primary record of impact compaction: it shows what the blows actually did to the fill.

Impact compaction is accepted in one of two ways: by demonstrating that the fill has densified, or by demonstrating that it has stopped settling. Most specifications use both, and most disputes come from using one where the other was intended.

Start with the level survey

The cheapest and most informative test is a survey of the surface before treatment, after each pass, and at the end of the plot. Settlement per pass shows whether the drum is still collapsing voids or has stopped achieving anything. It also shows whether the treatment is uniform: a plot where one strip settles far more than its neighbour has a soft spot or a different fill, and no single density test will tell you that. Survey the same points each time, on a grid, and record them.

What density and penetration tests prove

In-situ density testing (sand replacement, nuclear or gauge methods) measures the state of the material at the test location and depth. It proves a layer, not a mass. Dynamic cone penetration and cone penetration tests give a profile with depth and are better suited to showing whether treatment reached below the worked layer, but they remain point measurements in a variable fill. The practical rule: test at the depth the design cares about, in enough locations to represent the plot, and read the results alongside the settlement record rather than instead of it.

Plate load testing

Where the treated surface will carry structural load — slabs, crane rails, hardstanding — a plate load test gives a direct measure of deformation under load at the surface. It is a surface test: it says nothing about a loose layer two metres below. Used together with penetration profiles it answers the question a client actually asks, which is whether the ground will move under the load.

Proof rolling

Proof rolling with a loaded roller at specified axle loads is a qualitative check for soft spots and loose patches, and it is usually the last operation before pavement layers. It finds defects that point testing missed. It does not replace density testing, and a plot that passes proof rolling can still fail a settlement criterion.

Records that make acceptance possible

For each plot: fill type and source, layer thickness, drum class, pass pattern and direction, working speed, settlement after each pass, test locations with their results and depths, and the date. Without those records a result cannot be defended six months later when settlement appears elsewhere, and the next plot has to be treated as an unknown.

Mistakes that invalidate results

The recurring ones: testing only the top few hundred millimetres of a treatment designed to reach much deeper; taking one test per hectare in a fill known to vary; testing while the fill is still wet from placement; comparing before-and-after numbers taken at different points; treating proof rolling as a density result; and changing the pass pattern mid-plot without a new trial, so that the record no longer describes what was built.

Writing acceptance into the specification

Express acceptance as a performance requirement rather than a vague density figure: settlement over the final passes not exceeding a stated limit, plus density or penetration values at a defined depth and frequency, plus proof rolling at a defined load. State the test locations, depths, frequency and who witnesses them. A specification that says only "compacted to the required density" invites the argument it was written to avoid.

Test methods and what they answer

  • Level survey — did the fill settle, and where
  • Density test — state of the material at a point and depth
  • DCP / CPT profile — did treatment reach below the layer
  • Plate load — deformation under load at the surface
  • Proof rolling — soft spots and loose patches